Our Website uses cookies. Cookies are small text files held on your computer that help us understand how you use our Website. Our cookies do not store any personal information about you, and you can delete and block cookies via your browser settings at any time. By clicking “Ok” you agree to accept our use of cookies. Learn more by reviewing our privacy policy.

Starbucks Pad 3 - Yucaipa Point

Yucaipa, CA

Ground Up Starbucks Shell

Did someone say ground up completed in 3-1/2 months? That’s right!

Another great project by JG Construction Company at Yucaipa Point. JG started this project with a 4-1/2 month original schedule for the entire site and building shell. Having started with a few grading delays and obstacles needing to be overcome, our incredible team along with our clients amazing support to achieve common and aggressive goals, JG was able to deliver this building for Starbucks in 3-1/2 months! This project included grading, sitework & the entire shell building for out client to delivery to Starbucks.